Project Memorabilia

2006.12.28

CPI and the Ministry of Electric Power No. 1 of  Myanmar reached a memorandum of understanding(MOU) for cooperative development of  the Hydropower Projects in the Upstream Ayeyawady River Basin.

          2006
   

2008.02.27

The contract for the construction power plant (Chipwi Nge HPP) was signed.

          2008

2008.03.05

Construction the construction power plant (Chipwi Nge HPP) was commenced.

2008.11.04

The Hydro-power Projects in the Upstream Ayeyawady River Basin were approved by the State Council of China.

       

2009.03.27

The framework agreement on cooperative hydropower development between China-Myanmar government was signed.

          2009

2009.06.16

CPI and the Ministry of Electric Power No. 1 of Myanmar signed the Memorandum of Agreement(MOA) of  the Hydropower Projects in the Upstream Ayeyawady River Basin in Beijing.

2009.12.20

CPI Yunnan International Power Investment Co., Ltd. (CPIYN) and the Ministry of Electric Power No. 1 of Myanmar signed in Naypyitaw the Joint Venture (JV) Agreement of Myitsone HPP on the Upper Reaches of the Ayeyawady River.(JVA)

2009.12.21

The Groundbreaking ceremony of  Myitsone HPP was held on site.

   

2010.05.20

The Government of  Myanmar granted the concession right of  Myitsone HPP.

          2010

2010.06.03

CPIYN and the Ministry of  Electric Power No. 1  of  Myanmar signed in Naypyidaw the Joint Venture (JV) Agreement of Chipwi and Laza HPPs on the Upper Reaches of the Ayeyawady River.

2010.06.11

Upstream Ayeyawady Confluence Basin Hydropower Co., Ltd.(ACHC) was incorporated.

2010.12.21

The Groundbreaking ceremony of  Chipwi HPP was held on site.

           

2011.09.17

72-hour commissioning of all the units of  Chipwi Nge HPP was completed.

          2011

2011.09.30

The then president U Thein Sein delivered the message to parliament to suspend the Myitsone HPP in his term.

2011.12.16

The Government of  Myanmar granted the concession right of Chipwi HPP.

   

2013.09.23

Chipwi Nge HPP began to supply power to Myitkyina.

          2013
           

2015.01.20

The supplemental agreement of  the upstream Ayeyawady River basin hydropower Project and the JV agreement of Chipwi Nge HPP were signed.

          2015
   

2016.08.12

The investigation commission for the Hydropower Projects in the Upstream Ayeyawady River Basin was  established by Government of Myanmar.

          2016

2016.11.11

The investigation commission for the Hydropower Projects in the Upstream Ayeyawady River Basin submitted the first investigation report to president.